Q:
Multiple Issues in Putaway Process – DO-2609-0397
Module: Putaway Process
DO No.: DO-2609-0397
Total Item Lines: 7
Two issues have been identified for this DO:
Issue 1 – Line 1–3 Cannot Be Scanned
The PIC is unable to scan Line 1 to Line 3.
When attempting to scan Line 1–3, the items remain under “UnPick GRN” and do not move to “On-Picking GRN” after scanning.
Issue 2 – Scanning One Line Causes All Lines 4–7 to Move to “On-Picking GRN”
For Line 4–7, the PIC only scans one line. However, after scanning one of the lines, all Line 4–7 are automatically moved to “On-Picking GRN”, and the PIC proceeds to “Process”.
As a result, the PIC is unable to identify which specific line was actually scanned.
Kindly investigate the scanning and status update logic in the Putaway Process module for DO-2609-0397.
Attachments:
You must be logged in to view attached files.Join the conversation
You must be logged in to reply to this topic.
For DO-2609-0397, we found that the Receiving Department is different between the item lines:
We would like IT/vendor to confirm whether this difference is related to the issues previously reported in the Putaway Process.
Request for Rocher to check:
Kindly advise the source of this field and whether it is related to the issues observed in DO-2609-0397.